Owner: 
Florida Department of Transportation - District 1
Design team: 
Carter and Burgess, Inc.
Delivery method: 
Lump Sum, Hard Bid

The project consisted of the construction of three new bridges over the I-75 Canal, the widening and renovation of the existing Golden Gate Parkway Bridge, and the installation of a sound wall and two retaining walls.  Approximately half a mile of I-75 north bound and southbound and the existing roadways approaches to the interchange were reconstructed. Upgrades of existing drainage system, lighting system and landscaping were made.